Saturday, February 23, 2019

Section: avionics
Hours: 4

I finished up the ground wires for the main panel.

Friday, February 22, 2019

Section: avionics
Hours: 4

I was able to identify all but 8 of the ground wires and added wire labels to them. Today I started adding connectors to the grounds.


Thursday, February 21, 2019

Section: 50
Hours: 4

I worked on the throttle cable connection today.


Monday, February 18, 2019

Section: 49
Hours: 4

I fabricated and installed the sniffle valve line.



Friday, February 1, 2019

Section: engine
Hours: 4

I worked on routing the spark plug leads.


The spark plug wires should be spaced apart to prevent cross talk. I purchased several packages of these wire separators from Amazon.